Phase III:

Happy Friday to everyone.  Appaloosa is where my construction tech has been placing white flags.  He has completed the east west portion last week and I see some utilities have been marked.  Today, my construction tech was starting to flag routes on the north south part of Appaloosa.

 

The drop crew is finishing up in Edgewood Circle.  They will make their way to Appaloosa next week.  They will stay on Appaloosa until they have completed everyone who has signed up.

 

The splicing team that follows the drop crew was working in the Maple and Willow areas.  They will try and stay close to the drop crew.

 

The final group is the install team, where they have been active in the Foxfire area.  They will continue to move safely and quickly around the property.  We are doing our best to get everyone hooked up ASAP.

 

A request that I have for the residents in Loma Linda.  We have some terminals that are in the right of way, please do not deface these.  We discovered one today where an individual screwed something to our terminal.  These are designed to be waterproof and any holes in the unit could lead to outages down the road.  Thank you for understanding.

 

Have a wonderful weekend,

Todd Van Epps

 

Reach our Optic Customer Agents @ 855-806-7325 or https://optic-communications.com/cities/loma-linda-mo/

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *