General Manager Update (July 20, 2018)

7/20/18 General Manager’s Update

Phase III:

Happy Friday to everyone.  The drop installation crew has a couple areas that they’ve completed; Butterfield PL and Maple Dr.  They are still picking up customers as they progress along Butterfield but have spent a good portion of the last couple weeks in the Willow Lane & Willow Way area.  They should be finishing that area up early next week.

 

The splicing team that follows the drop crew completed their work in Butterfield PL, a few on Butterfield Drive, and the Fox Fire Dr. area.

 

My install team continues to work as safely and quickly as they can.  They have completed some work in the Rosebud Circle and Willow area.  I know these areas are further apart but the install crew will bounce around based on what appointments work for a particular customer.

 

I want to thank the customers that have allowed me to bring other Optic employees to their homes.  This allows for my office employees to see what the home installation process looks like.  It also allows me to see our new Optic customers and personally thank them.

 

Have a wonderful weekend,

Todd Van Epps

 

Reach our Optic Customer Agents @ 855-806-7325 or https://optic-communications.com/cities/loma-linda-mo/

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published.