General Manager Update (July 6, 2018)

7/6/18 General Manager’s Update

Phase III:

We at Optic Communications had a safe and happy 4th of July, I’m hoping that you all did as well.   I had the chance to drive around for a bit this morning and wanted to say thanks to the people I had a conversation with.  Please be careful in this heat. Now to the latest update.

 

Our drop team observed some extra holiday time off this last week so there was not as much activity completed as normal weeks.  They will be back in action starting right away on Monday and continue with the motion they started in the Willow area. They also started to place piping in the Butterfield Place area so we continue our progress across Butterfield.  All the rock in the Loma Linda makes for a slower working process, but the team is persistent and they do a quality job.

 

One of our splicers was at the intersection of Rosebud & N Loma Linda Dr.  Watch for those trailers to be parked in strategic areas, that is when the fiber is being put together to transmit light up to your premise.  They will continue to follow the drop team around.

 

My install team continues to get services installed quickly and we appreciate you making and keeping appointments so we can move to your neighbor quickly.

 

Thank you,

Todd Van Epps

Reach our Optic Customer Agents @ 855-806-7325 or https://optic-communications.com/cities/loma-linda-mo/

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published.